0%

2013

Year

Construction and commissioning of Krasnodon
25 MW wind park
, the first in the Luhansk region.

The start of Lutuginsky 25 MW wind park.

Commissioning of the Kerch 25 MW wind park.

The company was the first among the companies in the
CIS countries that received 48.8 million euros of funding 
from the European Bank for Reconstruction
and Development.

The portfolio of promising projects in the Luhansk region 
with the total capacity of 875 MW has been formed

The extension of Vitroenerhoprom has been implemented
by building additional 5 MW.

«Fuhrlaender Windtechnology» LLC has signed
the license agreement with Wind to Energy Gmbh company 
expanding its range with three modern turbines with
the capacity of 2.0, 3.0 and 3.2 MW.

«Fuhrlaender Windtechnology» LLC has won the tender
for the EDS-contract for the supply of 22 2.0 MW 
turbines
 (made by SMARUK ENERGY company)
for Ereymentau 45 MW wind park in Kazakhstan.

History 2013
2010
2011
2012
2013
2014
2015
2016
2017
2018